Site Update 18th May 2018

Following the successful completion of the capping, plans have now been agreed with the Environment Agency (EA) that will enable us to start to accept waste back in to the landfill site. This will start on Monday 21st May and will be a phased process working to a methodology that has been developed in conjunction with, and agreed by, the EA. These plans have also been presented to and discussed with representatives from the Site Liaison Committee at our meeting…

0
Read More

Site Update 4th May 2018

Work has been undertaken this week to improve the seal on the capping in a couple of small areas in the southeast corner of the site. This work is now complete and we are confident that there is an adequate seal in place. We will continue to monitor the site to ensure that there are no further areas that require attention. Discussions have continued with the Environment Agency to develop a plan that will enable us to start to accept…

0
Read More

Site Update 27th April 2018

Having successfully anchored the capping using the long reach excavator we expect the work in the southeast corner of the site to be completed today. We are also confident that the three new pin wells will be connected to the existing infrastructure and will start collecting landfill gas from this area. This concludes the planned capping works and we will continue to monitor the site to ensure that there are no further areas that require attention. We are now entering…

0
Read More

Site Update 26th April 2018

Whilst the majority of the capping work in a smaller area in the southeast of the site is now complete, the severity of the slope is making it difficult for the team to get a seal down the westerly side. As a result, we are having to bring in a specialist long reach excavator. This will enable us to dig a trench into which the plastic cap will be anchored to produce a seal. Whilst we are not experiencing a…

0
Read More

Site Update 24th April 2018

The work to cap a much smaller area in the southeast corner of the site that was still emitting an odour has progressed well. The plastic capping is now complete and the work to install three additional pin wells (to extract the landfill gas) has begun. The engineering team are aiming to have all the work completed by the end of the week. We will provide a further updates via our website and Twitter feed @QuerciaLtd. Photo – work to…

0
Read More

Site Update 13th April 2018

The major engineering works to install a temporary plastic cap and seal an area of approximately 8600sqm was completed earlier this month. This work also saw the installation of a network of additional landfill gas collection lines under the cap to capture the surface emissions. This work has significantly reduced the odour and as a result we have now been able to identify a much smaller area in the southeast corner of the site that is still emitting an odour…

0
Read More
Quercia Ltd

Clayton Hall Sand Quarry
Dawson Lane
Whittle-le-Woods
PR6 7DT

Environment Agency
Clayton Hall Landfill Site Information

Latest News
Follow Us
©2018 Quercia Ltd. All rights reserved.